Simple and easy payment plan
Phase | Payment Percentage |
Booking Deposit (Aug 2014) | 15% |
On Mobilization (Oct 2014) | 15% |
On Completion of Basement (Jan 2015) | 10% |
On Completion of 2nd floor Slab (Feb 2015) | 10% |
Completion of 5th floor Slab (May 2015) | 10% |
On Completion of 8th floor Slab (Aug 2015) | 10% |
Delivery of Glass on Site (Dec 2015) | 10% |
Handover (March 2016) | 20% |